How long does planning permission take?
The short answer: 8 weeks for the council to decide once they’ve validated your application. The real answer, including everything between “I want to extend my kitchen” and “I have a decision”, is usually 3 to 6 months. This guide walks through each stage with realistic timelines, what causes delays, and how to avoid the most common pitfalls.
Before you wait 3 months
Your approval odds + 5 nearest comparables & refusal reasons.
Get my report — £9See a sample →The full timeline, stage by stage
Most homeowners underestimate how long the whole process takes because they only think about the 8-week council decision. Here’s everything:
Brief your architect or designer, iterate on designs, finalise drawings (site plan, floor plans, elevations, maybe sections and a design statement). Most of this time is back-and-forth on the design, not actual drawing time. Rushing this stage is the most common cause of later refusals.
Submit a pre-app query to your council, get a non-binding opinion from a planning officer. Useful for borderline projects or conservation areas. Councils take 2–4 weeks to respond. Costs £50–£500. Skip if your project is simple and obviously within policy.
Upload your application to the Planning Portal (the national submission site) or your council’s own portal. Pay the £548 fee. Wait for the council to validate: they check that you’ve included all required documents, plans, and certificates. For a complete submission this takes 1–2 weeks. For an incomplete submission, expect 2–4 weeks of back-and-forth before the 8-week clock starts.
Once validated, the council advertises your application and notifies neighbours. The consultation period is 21 days. Neighbours can object, support, or comment. This runs in parallel with officer assessment, so it doesn’t add separate time to the 8-week statutory target — but objections can trigger additional investigation, site visits, or committee referral.
The statutory 8-week target. During this period the officer reviews your proposal against local plan policy, visits the site if needed, consults internal experts (highways, heritage, drainage, trees), considers objections, and makes a recommendation. Most householder applications are decided under officer delegation. If the application goes to a planning committee, add 4–6 weeks more.
The council publishes a formal decision notice: approved, approved with conditions, or refused. Conditions often require specific materials, construction details, or mitigation measures. You can start work as soon as you have the decision notice (and building regulations approval), and permission lasts 3 years from the decision date.
Realistic total timelines
| Application type | Best case | Typical | Worst case |
|---|---|---|---|
| Householder planning | 10 weeks | 14 weeks | 6 months (if refused & resubmitted) |
| Lawful Development Certificate (LDC) | 6 weeks | 8–10 weeks | 12 weeks |
| Prior Approval (larger rear extension) | 42 days | 42 days | 42 days (statutory hard cap) |
| Listed building consent | 10 weeks | 14 weeks | 6+ months |
| Planning appeal (written representations) | 4 months | 6 months | 9+ months |
How to shorten the timeline
- Make sure your first submission is complete. The biggest avoidable delay is submitting with missing documents. Your architect should use a pre-flight checklist against the council’s local validation requirements.
- Use pre-application advice for borderline cases. A £250 pre-app that identifies a design flaw before you apply saves you the full 8–12 week cycle of a refused application.
- Check if your project is actually permitted development. An LDC is 6–10 weeks with a £274 fee; a full application is 10–14 weeks with a £548fee and higher architect costs. If you qualify for LDC, use it.
- Pick a designer who knows your council. Familiarity with the local validation checklist, common refusal reasons, and officer preferences cuts weeks off the submission-to-decision cycle.
- Respond to officer queries fast. If an officer asks for additional information during the 8-week period, the clock pauses. Respond within a day or two, not a week.
Worried about spending 12 weeks only to get refused?
Our £9 Full Report gives you a personalised approval probability, the 5 nearest comparable decisions from real recent applications, the most common refusal reasons at your council, and a concrete action plan — before you commit to 3+ months of planning process. Delivered as a PDF. Get my report — £9 or see a sample report →
Frequently asked questions
Check if you even need to wait
Many home improvement projects are permitted development and don’t need a planning application at all. Check your specific project in 2 minutes, free.
Check my project — free